Capital Projects and Facility Planning

Questions or comments: Contact B&G (For service questions contact the Service Response Center at x5555)

When necessary, advisories will be emailed to the occupants of buildings when power or other service interruptions are necessary.

FY 2008/09

Campus Renewal and Improvement Projects

No Building Project Description Program/Dept Contact Project Manager Project Mgr Phone Project Status (Schedule and Potential Campus Disruptions)
 




 




 




 




 




 




 




1 Alumnae House Restoration of existing rooftop chimneys, repairs to slate roof, replacement of freight elevator Martha Berry Bryan Corrigan 7631 Work to begin after Reunion in coordination with Alumnae House events
 




 




 




 




 




 




 




2




Alumnae House




Replacement of the interior freight elevator




Pat Lichtenberg




Bryan Corrigan




7631




Construction Schedule: Work to begin after Graduation in coordination with Alumnae House events




3




Alumnae House




Restoration and selective replacement of existing slate roof




Pat Lichtenberg




Bryan Corrigan




7631




Construction Schedule: Work to begin after Graduation in coordination with Alumnae House events




 




 




Josselyn, ADA accessibility & elevator




 




Corrigan, Bryan




7631




 




 




 




Quad Residences, fire door replacement (Strong, Raymond)




 




Corrigan, Bryan




7631




 




 




 




Josselyn, roof/masonry/window replacement




 




Corrigan, Bryan




7631




 




 




Alumnae House




Ongoing analysis and upgrade of egress




 




Corrigan, Bryan




7631




 




2 Aula Replace two sets of main entrance doors Kathy Bush /Ben Lotto Patrick Gilchrist 5996 Minimal disruption. Will need to be scheduled when no events are planned.
3 Chilled Water Plant Control Systems Improvements to automated controls for energy savings and improved delivery of chilled water. Betsy Eismeier Patrick Gilchrist 5713 Building occupants to receive 3-days notice of any disruptions to building service
 




Alumnae House




Alumnae House, parking/exterior lighting/sidewalks




 




Corrigan, Bryan




7631




 




 




Alumnae House




Alumnae House, restroom and pub partial renovations




 




Corrigan, Bryan




7631




 




4 Boathouse The installation of new docks Sharon Beverly Jeff Horst 5686 To be coordinated with Athletics
5 Campus Lighting Improvements to lighting in the North and South Parking lots and the pedestrian pathway from Raymond Avenue to the Townhouses Kiki Williams / Antonia Sweet Patrick Gilchrist 5996 Disruptions will be limited. Use of the pedestrian pathway to the Townhouses to be coordinated with Summer Programs
 




 




Presidents House, bathroom upgrades 4 total




Betsy Eismeier




Corrigan, Bryan




 




 




 




 




Presidents House, chimney repairs




Betsy Eismeier




Corrigan, Bryan




 




 




 




 




Presidents House, masonry/roofing repairs




Betsy Eismeier




Corrigan, Bryan




 




 




 




 




 




Betsy Eismeier




 




 




 




8




Campus Roadways




General repairs to be specified




Betsy Eismeier




Jeff Horst




5686




Campus Community to receive 24 hours notice of disruptions to roadways




1




 




Science, New Building




Betsy Eismeier




Jeff Horst




7868




 




 




 




Science, planning and design fees




Betsy Eismeier




Jeff Horst




7868




 




 




 




Wimpfheimer, renovation including temporary space




Betsy Eismeier




Jeff Horst




7868




Does this include sprinklers?




 




 




Wimpfheimer, space relocation study




Betsy Eismeier




Jeff Horst




7868




 




8




Aula




Replace structural beams and flooring




Betsy Eismeier




Jeff Horst




7868




 




 




 




Swift, renovation




Betsy Eismeier




Jeff Horst




7868




 




 




 




Rockefeller Hall, masonry/roof/window replacement (3 years)




Betsy Eismeier




Jeff Horst




7868




 




 




 




 




Betsy Eismeier




Jeff Horst




 




 




 




 




 




Betsy Eismeier




Jeff Horst




 




 




 




 




Chicago Hall, roof replacement




Betsy Eismeier




Jeff Horst




 




 




 




 




 




Betsy Eismeier




Jeff Horst




 




 




 




 




Warehouse, CIS backup server room completion




Betsy Eismeier




Jeff Horst




7268




Close to Completion




6 Campus Roadways Repairs to Old Silvermine and Lockwood Roads Dana Kleinhans Jeff Horst 5686 Building occupants to receive 3-days notice of any disruptions to access
10




Campus Roadways




Repairs to the South Gate to the President's House




Betsy Eismeier




Jeff Horst




5686




Campus Community to receive 24 hours notice of disruptions to roadways




7 Central Heating Plant Improvements to controls; replacement of boiler stack inside plant. Betsy Eismeier Patrick Gilchrist 5713 No disturbance to building occupants anticipated.
12




Central Heating Plant




Replacement of boiler stack inside the central heating plant




Betsy Eismeier




Patrick Gilchrist




5713




No disturbance to building occupants anticipated.




8 Chapel Replacement of the tower roof Sam Speers Art Fisher 7268 To be coordinated with building occupants and events
9 CIS Building Roof replacement and exterior wall masonry repairs Bill Terry Art Fisher 7268 To begin following Graduation
 




 




 




 




 




 




 




 




 




Library Thompson), roof and gutter replacement




 




Fisher, Art




 




 




 




 




Powerhouse Theater, masonry repairs




 




Horst, Jeff




 




 




 




 




Ely Hall, roof/masonry/window replacement, 3 phases




 




Horst, Jeff




5686




 




10 College Center Air handlers replacement to improvement ventilation and air conditioning to the Bookstore and College Center atrium Michelle Ransom /Terry Quinn Patrick Gilchrist 5713 Building occupants to be notified with 24-hours notice of any disruptions to building service
11 Davison House Complete interior renovation, accessibility, systems, roof replacement, and restoration of exterior masonry. Residential Life - Luis Inoa Bryan Corrigan 7631 Davison to close after graduation and re-open for fall 2009. Construction staging on Joss Beach to begin mid-May. Quad side disturbance to include trenching for new steam line.
17




Electrical Upgrade




Electric meters, various buildings




Kiki Williams




Patrick Gilchrist




5713




Building occupants to receive 24-hours notice of any disruptions to building service




12 Faculty Housing Approximately 38 projects for various levels of renovation to faculty housing Alison O'Brien / Louise Crans Jeff Horst 5686 Construction Schedule: To be scheduled with individual building occupants
19




General Life Safety Equipment




This is a phased program that will address upgrades to existing life safety systems as well as address elevator deficiencies




Betsy Eismeier




Kiki Williams




5996




Building occupants to receive 24-hours notice of any disruptions to building service




 




 




North Lot, parking lot expansion




Betsy Eismeier




Horst, Jeff




5686




 




20




HVAC Controls




Bldg HVAC Control Upgrades




Betsy Eismeier




Gilchrist, Patrick




5713




Building occupants to be notified with 24-hours notice of any disruptions to building service




13 Kautz House Partial reconfiguration of the 1st Floor to create and additional office David Borus Laura O'Connell 7507 First floor work to be scheduled during the summer but Kautz House to remain open.
14 Kautz House Refinishing the wooden porch David Borus Kiki Williams 5996 To be coordinated with building occupants and events
15 Lathrop House Replacement of the water heater in the basement of Lathrop House Residential Life - Luis Inoa Kiki Williams 5996 Building occupants to receive 3-days notice of any disruptions to building service
 




 




Baldwin, parking lot relocation




 




Horst, Jeff




5686




 




 




 




Sidewalk and lighting improvements: Juliet Gate to North Parking Lot




 




Horst, Jeff




5686




 




 




 




Sidewalks and site amenities




 




Horst, Jeff




5686




 




 




 




Signage (exterior)




 




Horst, Jeff




5686




 




 




 




Roadway: Loop around Main Bldg (paving)




 




Horst, Jeff




5686




 




 




 




Blodgett, parking lot restoration




 




Horst, Jeff




5686




 




16 Library (Lockwood) Exterior work to replace deteriorating sealants and masonry Sabrina Pape Laura O'Connell 7507 Exterior work to remediate water penetration
 




 




Pratt House, renovation




 




Laura O'Connell




5686




No program or scope to date




 




 




Lathrop, masonry restoration & new roofing




 




Laura O'Connell




5686




 




 




 




Study South Parking Lot Expansion




 




Laura O'Connell




5686




 




 




 




 




 




Laura O'Connell




 




 




17 Library (Van Ingen) Renovation of the 4th Floor Art Library reading room including construction of a new connecting stair to the 3rd Floor stacks Sabrina Pape Laura O'Connell 7507 To begin following Graduation
 




Sanders Classroom




Sanders Classroom, roof replacement




 




Laura O'Connell




7507




 




18 Library (Van Ingen) Extensive exterior restoration of masonry, repairs to existing windows, replacement of the roof and structural repairs to the roof slab Sabrina Pape Laura O'Connell 7507 Work will begin immediately following Reunion Weekend and continue through September 2009. Construction zone from Main Gate on both sides of Van Ingen Hall.
 




 




Library Thompson), ADA accessible elevator, north end




 




O'Connell, Laura




7507




Renovations will begin immediately following Commencement on May 25th 2008. The first phase scope is to be finalized.




 




 




Library Thompson), compact shelving and learning centers




 




O'Connell, Laura




7507




Renovations will begin immediately following Commencement on May 25th 2008. The first phase scope is to be finalized.




 




 




Library Thompson), planning study




 




O'Connell, Laura




7507




Renovations will begin immediately following Commencement on May 25th 2008. The first phase scope is to be finalized.




 




 




Library Thompson), replace air handlers




 




O'Connell, Laura




7507




Renovations will begin immediately following Commencement on May 25th 2008. The first phase scope is to be finalized.




19 Main Building Replacement of the air conditioner serving the 2nd Floor (south) Betsy Eismeier Patrick Gilchrist 5713 Building occupants to be notified with 24-hours notice of any disruptions to building service
20 Main Building Replacement of carpet and improvement of lighting in the 1st Floor South Corridor Betsy Eismeier Kiki Williams 5996 To be coordinated with Career Development, Financial Aid, and other offices
21 Mudd Chemistry Replacement in kind of the existing Bohn rooftop air conditioning unit & cooling tower Sarjit Kaur Patrick Gilchrist 5713 Building occupants to receive 3-days notice of any disruptions to building service
22 Mudd Chemistry Installation of a new generator Sarjit Kaur Kiki Williams 5996 Building occupants to receive 3-days notice of any disruptions to building service
 




 




FLLAC clean brick façade




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




FLLAC, new flat roof on walkway, planning fees




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Taylor, roof/masonry/gutter replacement




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




 




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Life Safety, fire escape renewal plan




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Ely Hall, exterior door replacement




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Chicago Hall, main door replacement (4 sets)




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Sanders Physics, roof replacement




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




New England, dormers and structural steel repairs




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Olmsted, masonry repairs




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Rockefeller Hall, exterior door replacement




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Main Bldg, bathroom stacks




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Raymond House, masonry repairs




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Strong House, masonry repairs




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Lathrop, renovation




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Cushing House, roof replacement




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Cushing House, bathroom stacks




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Juliet, transfer to College Properties, LLC




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Main Bldg, 2nd Floor Central electrical /renovation & architectural improvements




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Main Bldg, 1st Floor South electrical /renovation




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Main Bldg, 2nd fl North electrical/renovation




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Baldwin Hall, roof repairs




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Chapel, ADA access & bathroom renovation




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




 




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Cable Plant, interior & exterior data wiring




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




 




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




 




 




 




 




Kiki Williams




 




Building occupants to receive 3-days notice of any disruptions to building service




?




 




Blodgett Hall, replace basement A/C




 




Kiki Williams




5713




Building occupants to receive 3-days notice of any disruptions to building service




23 New England General bathroom upgrades Ben Lotto Kiki Williams 5996 Building occupants to receive 3-days notice of any disruptions to building service
 




 




Olmsted, Air Handling Unit 1 & 2 Replacement




 




Gilchrist, Patrick




5713




 




 




 




Olmsted, autoclave replacements




 




Gilchrist, Patrick




5713




 




 




 




Powerhouse Theater, Air Handling Unit replacement, chill water upgrade




 




Gilchrist, Patrick




5713




 




24 New Hackensack Interior Renovations in preparation for the temporary move of Wimpfheimer Nursery School to New Hackensack during the summer of 2009 and, fro the relocation of the Thompson slide library and Art Department Faculty in connection with the Van Ingen renovations. Julie Riess/ Harry Roseman Laura O'Connell 7507 To be coordinated with relocations associated with Van Ingen porjects during the summer of 2008
25 North Edge of Campus/Raymond Avenue Liaison Coordination of work with DOT and Central Hudson, landscaping, pathways, lighting Betsy Eismeier Jeff Horst 5686 Work continuing through November of 2008
26 Maria Mitchell Observatory Interior renovations, window replacement and landscaping; creation of seminar room in dome, new offices for Education and College historian, with recognition of historic purpose of building through original equipment displays, photos, plaques. Chris Bjork Bryan Corrigan 7631 Work continues this summer. Pedestrian walkway disturbances will occur as the contractor makes connections to chilled water lines due north of the Observatory east of Pratt House. New path to be created from Metcalf to the main entrance of the Observatory.
33




 




Swift, electrical upgrade




 




Gilchrist, Patrick




5713




 




27 Prentiss Fields New Athletic Facilities Andy Jennings Art Fisher 7268 While not a summer project work will be ongoing to complete the project throughout the summer. Disruptions to be coordinated with Summer Programs
28 Powerhouse Theatre Install a new wood floor in performance area Chris Grabowski Naomi Davies 7868 Scope to be determined and work scheduled in coordination with Summer Programs
29 Rockefeller Hall Classroom Committee Renovations to Rockefeller Hall classrooms including technology upgrades. Ben Lotto Laura O'Connell 7507 Renovations will begin immediately following commencement on May 25th 2008. The first phase scope is to be finalized.
30 Rockefeller Hall Upgrades the ground floor Men's Bathroom Ben Lotto Patrick Gilchrist 5713 This bathroom will be off line during the summer. Building occupants will be directed to other facilities within the building.
31 Sanders Classroom Phase I of two-year upgrade of Butler Auditorium. 2008 work to include remediation of heating and cooling systems. Ben Lotto Laura O'Connell 7507 Renovations to begin after Reunion Weekend
37




 




Chill water line replacement, Van Ingen to Thompson




 




Gilchrist, Patrick




5713




 




32 Sewer Lines New sanitary lines between FLLAC and the President's House; additional work behind Pratt House. Betsy Eismeier Williams, Kiki 5996 Building occupants to receive 24-hours notice of any disruptions to building service
38




 




Boiler Plant, new vfd's




 




Gilchrist, Patrick




5713




 




33 Skinner Hall Repairs to the east external stair, restoration of north elevation buttress, and repairs to roof and drains Karen Murley Jeff Horst 5686 Skinner Hall will be closed during the Summer 2008 to accommodate restoration work. Access will be limited to Music Department faculty and staff.
40




Skinner Hall




Restoration of the north elevation buttress




Karen Murley




Jeff Horst




5686




Skinner Hall will be closed during the Summer 2008 to accommodate restoration work. Access will be limited to Music Department's administrative staff.




 




Skinner Hall




General repairs to the roof and drains




Karen Murley




Jeff Horst




5686




Skinner Hall will be closed during the Summer 2008 to accommodate restoration work. Access will be limited to Music Department's administrative staff.




 




 




Boiler Plant, oil tank maintenance




 




Jeff Horst




5713




 




 




 




Boiler Plant, replace water storage tanks for heating plant




 




Jeff Horst




5713




 




 




 




Residence Halls, install new lock cores in student room doors




 




Jeff Horst




5713




 




41




 




College Center, air handlers phase 1




 




Jeff Horst




5713




 




34 Smokestack Repair and reconstruction of the smokestack Betsy Eismeier Jeff Horst 5686 No disruption to campus occupants anticipated
35 Steam Line From Rocky to Josselyn Replacement of steam line Luis Inoa Bryan Corrigan 5996 Trenching to begin immediately following graduation
 




 




Old Laundry Bldg, Air Handling Unit & Condensing Unit, 2nd fl




 




Gilchrist, Patrick




5713




 




43




 




 




 




 




 




 




36 Steam line near Wimpfheimer & Blodgett Replacement of steam line Betsy Eismeier Kiki Williams 5996 Trenching between Wimpheimer and Blodgett to begin following Graduation. Campus occupants will receive 24 notification of any disruptions to parking
37 Storm Water Drainage New storm water drainage system to eliminate water pooling and building damage at the Students' Building, Noyes, Jewett, and Davison. Betsy Eismeier Kiki Williams 5996 Trenching between Kenyon, Students Building and Davison to begin following Graduation.
38 Students' Building Interior renovation of the ACDC food services area Maureen King Tom Allen 7267 Renovations to begin immediately following Graduation, with coordination for Reunion Weekend and Summer Programs.
39 Students' Building Loading dock roof replacement and masonry repairs Michelle Ransom Art Fisher 7268 No disruption to campus occupants anticipated
 




 




Sanitary Line, feasibility study




 




Williams, Kiki




5996




 




47




 




Steam Line, Strong to Lathrop




 




Williams, Kiki




5996




 




40 Students' Building Repairs to the columns at the main entrance and repairs to the wooden sofit details at the roof line Michelle Ransom Art Fisher 7268 No disruption to campus occupants anticipated
41 Tennis Courts Reconfiguration and resurfacing of northern-most tennis courts Sharon Beverly Jeff Horst 5686 To be coordinated with Athletics
 




 




Storm Drainage, Students Building to Strong




 




Williams, Kiki




5996




 




49




 




Water tank (300,000 gallon ) removal




 




Williams, Kiki




5996




 




42 Town House Road and Site Improvements Widening and improvement of TH roadway, upgrades of sidewalks and lighting. Luis Inoa Art Fisher 7268 Anticipated to begin in May 2008. Construction permits pending
 




 




B & G, emergency generator




 




Williams, Kiki




5996




 




 




 




Barn, roof replacement




 




Williams, Kiki




5996




 




 




 




Boiler Plant, replace main controls




 




Williams, Kiki




5996




 




 




 




Terrace Apts, replace primary electrical line




 




Williams, Kiki




5996




 




50




 




Walker, emergency generator




 




Williams, Kiki




5996




 




43 New Town House Apartments Construction of three new buildings in apartments (50 students). Scope includes installation of geothermal heating and cooling, all accessible buildings. Luis Inoa Art Fisher 7268 Offline immediately following Graduation until early arrivals in August 2008.
44 Various Buildings Installation of emergency siren Betsy Eismeier/ Sabrina Pape /Sharon Beverly Jeff Horst 7268 Installation of emergency siren system on various buildings on campus
45 Walker Field House Replacement of air handler for improvements to ventilation systems serving the pool Sharon Beverly Patrick Gilchrist 5713 Building occupants to receive 3-days notice of any disruptions to building service
 




 




Noyes, elevator replacement




 




Williams, Kiki




5996




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Terrace Apts, replace transformers




 




Williams, Kiki




5996




Building occupants to receive 3-days notice of any disruptions to building service




 




 




College Center, solar panels




 




Williams, Kiki




5996




Building occupants to receive 3-days notice of any disruptions to building service




 




 




Students Bldg, freight elevator repairs




 




Williams, Kiki




5996




Building occupants to receive 3-days notice of any disruptions to building service




52




 




Students Bldg, replace transformers 208 VAC & 480 VAC




 




Williams, Kiki




5996




Building occupants to receive 3-days notice of any disruptions to building service




46 Walker Field House Bathroom upgrades Sharon Beverly Kiki Williams 5996 Building occupants to receive 3-days notice of any disruptions to building service
 




 




Boiler Plant, spill containment measures




 




Kelly, Jim




 




Building occupants to receive 3-days notice of any disruptions to building service




53




 




Walker, parking lot & basketball




 




TBD




 




Building occupants to receive 3-days notice of any disruptions to building service




47 Water Lines New water lines from Kenyon to Jewett Betsy Eismeier Kiki Williams 5996 Building occupants to receive 3-days notice of any disruptions to building service